In UAE construction contracts, a percentage of each certified payment is commonly retained by the employer until completion or the end of the defects period. Under VAT, the date of supply for the retained amount generally arises when it becomes due or is paid, and the Guidelines v1.1 addressed retention following pilot questions. On e-invoices this means the progress invoice covers the certified amount with retention shown clearly, and the retention is invoiced electronically when it falls due, referencing the contract. Systems must track retention balances per contract for the life of the project.
Key facts at a glance
- Retention is typically 5–10% of each certified payment, held until completion or end of defects liability.
- VAT date of supply for retention generally arises when it becomes due or is paid.
- Progress invoices present the certified amount; retention is tracked and invoiced on release.
- Release invoices may come months or years later and must reference the contract.
- Addressed in Guidelines v1.1 (1 June 2026) after pilot feedback.
Two presentation approaches
| Approach | Progress invoice shows | Retention invoice |
|---|---|---|
| Invoice certified net of retention | Work done less retention; VAT on the net | Separate e-invoice when retention falls due, VAT on retention |
| Invoice gross with retention noted | Full certified value; VAT on gross; note retention held | No further invoice; employer pays retention later |
Which approach is correct depends on the contract terms and the VAT date-of-supply analysis for retention under the Decree-Law and the Guidelines. Many UAE contractors invoice net of retention and invoice the retention on release; confirm your treatment with your adviser and apply it consistently across projects.
Modelling it in PINT AE
For the net approach, the progress invoice lines reflect the certified work and a document-level allowance or an explicit line reduces for retention, with the reason text identifying it as retention and the contract reference carried. The later retention invoice is a normal 380 document with a line describing the retention release, referencing the contract and, where helpful, the progress certificates. Avoid representing retention as a negative line without a reason.
System requirements
Common errors
Forgetting to invoice retention when it becomes due; invoicing retention without a contract reference, so the employer's AP cannot match it; and changing presentation approach mid-project, which confuses both parties' VAT records. The ten-year life of some projects means staff turnover; the system, not memory, must hold the obligation.
Where Zaini Developers fits in
Our construction billing module keeps a retention ledger per contract, generates progress e-invoices under your chosen presentation, and alerts when retention falls due so the release invoice goes out on time with the right references.
Book a free consultation →Frequently asked questions
Is VAT charged on retention when the work is certified or when it is paid?
Generally when the retention becomes due or is paid, subject to the date-of-supply rules; confirm with your adviser for your contract terms.
Can one retention invoice cover several projects?
Issue one per contract; the employer's matching and your audit trail depend on the contract reference.
What if the employer deducts from retention for defects?
Invoice the amount actually released; the deduction is not a supply by you.
How do subcontractors handle retention they suffer?
The same logic applies in reverse: track retention receivable per contract and invoice on release.