Weeks 1 to 4: data and decisions. Weeks 5 to 8: provider, appointment and connection. Weeks 9 to 12: testing, training and parallel run. Start the plan at least 90 days before your go-live date, and earlier if your software cannot produce PINT AE.
Key facts at a glance
- Assign one owner for the project, even in a small company.
- Customer data starts in week 1 because it depends on other people.
- Ask your software vendor about PINT AE in writing by week 3.
- Appoint your provider in EmaraTax by week 7 at the latest.
- Finish with two weeks of parallel running before go-live.
Weeks 1 to 4: data and decisions
Weeks 5 to 8: provider and connection
Weeks 9 to 12: test and go live
Who does what
| Task | Typical owner |
|---|---|
| Customer data | Sales or accounts |
| Catalogue and VAT categories | Accounts with tax adviser |
| Software decision | Owner or IT |
| Provider and EmaraTax | Owner or finance |
| Testing | Accounts with IT or developer |
When 90 days is not enough
If your software cannot produce PINT AE and needs replacing, add the time for that project. Check your exact dates with the deadline calculator.
Frequently asked questions
How long does it take a small business to get ready for e-invoicing?
Around 90 days for a typical small business with software that can be connected. Longer if the software must be replaced.
What should we do first?
Name an owner and start collecting customer data, because it depends on your customers responding.
When should we appoint our provider?
Around week 7 of a 90-day plan, and in any case before your phase deadline, which is 31 March 2027 for most SMEs.
What is a parallel run?
Generating and validating every invoice through the new process before it is mandatory, so you can fix problems without penalty risk.